East Veterans School Building Project
Opening Fall 2023
Upcoming Events
School Building Committee meeting: Thursday, June 8, 2023 at 4:30 p.m. (Please note time)
May 11, 2023
Brian Hromadka of CBRE/Heery reported that the project remains on time and on budget. The switchgear issue has been resolved by securing rental gear that can power the whole building. The permanent switchgear is scheduled to be delivered in July. BH also reported that the Information Technology switchgear is on target for delivery.
Building B finishes are progressing nicely. Furniture is schedule to arrive on time. The move planning process is underway for EGS and Veterans' Memorial.
Alex Corbett of WT Rich presented a drone video of the project (around the 35 minute mark of the meeting.)
April 13, 2023
Brian Hromadka of CBRE/Heery reviewed progress on the project including exterior fencing, interior casework in the classrooms, and installation of gymnasium flooring nearing completion.
Jon Rich of WT Rich reported there is a delay in receiving electric switch gear that will provide permanent power to the school. This delay was learned two days before the long-scheduled ship date. JR said delays of this type of equipment is a nationwide issue that has worsened since the pandemic. JR is confident testing of systems can continue on schedule with the temporary switch gear on site and with other switch gear that can be rented. JR also said they have identified and are evaluating an alternate product that is available and its compliance with specifications to power the whole school. JR stated that the solution should be known in the next couple of weeks and is "highly confident" the project team will navigate this issue for an on-time opening of the new school.
BH reported that a move manager has been brought on board to coordinate EGS and Veterans' Memorial move into the new school. BH also reported that the MSBA will reimburse a portion of the change order for the cell service boosted.
The SBC voted to authorize equipment purchases not to exceed $160,000.
March 9, 2023
As reported by Brian Hromadka of CBRE/Heery, the project remains on track for the substantial completion date which is about 3 months away. In Building A, millwork, flooring and ceilings are well underway. In Building B, dry wall installation is nearing completion, gymnasium equipment has been installed.
The current challenge is securing permanent power to the site as National Grid has been having supplier issues, but is working hard to meet the target date for installation. A power outage is scheduled for March 13 (rescheduled from February) related to installing a generator which will provide power to the site for approximately one week. Notices have been sent out to affected addresses.
The Committee approved procurement for Technology in an amount not to exceed $690,000 which is approximately $58,000 under budget. This amount will be used to offset overages in the furniture budget. The City and schools are in the process of purchasing a city-wide phone system will may also create additional savings.
Alex Corbett of WT Rich presented an Open Space tour of the site. The public is encouraged to view the project progression in these video updates which are usually presented at the end of the meetings. Please see Meeting Recordings.
Finally, the Committee discussed and agreed to moving the meeting time of future meetings to 4:30 pm to accommodate schedule conflicts.
February 27, 2023
The Committee met to review and approve purchase orders for Furniture, Fixtures and Equipment (FF&E). Brian Hromadka of CBRE/Heery reviewed the selection process which included feedback from educators and other staff. The FF&E cost is approximately $100k over budget primarily due to purchasing individual desks for classrooms as opposed to tables which accommodate 4-6 students each. This change was made so there is more flexibility in the classrooms. The total approved for FF&E was $737,811 and $24,934 which is part of the technology budget.
February 9, 2023
Brian Hromadka of CBRE/Heery reported that finishes are moving forward in Building A and the elevator installation is complete. In Building B, dry wall installation is nearly finished and MEP rough ins are complete. Work has been happening on most Saturdays.
Commissioning Agent - BH explained the each MSBA project has a commissioning agent that works under the MSBA. BH introduced Michael Papagni from NV5 who is the systems commissioning agent on the project. MP explained that he reviews systems installed as the project moves along and responds with any issues in the design elements. He provides comments back to the MSBA and the project team. Corrective actions get logged and subcontractors rectify the items. MP / NV5 will come back 10 months after substantial completion to look for any deficiencies, test energy uses as compared to the design plan, and direct fixes which are taken care under warranty. There is also an Envelope Commission agent, Russell Young with BEA.
BH reviewed the work that was able to be reclaimed in project scope - concrete benches, raised planting beds, outdoor trash receptacles, bollards vs boulders, some plantings on the steep slope.
BH also reported that submissions of invoices to date are being made to the MSBA and reimbursements will be forthcoming.
A community update - National Grid will need to shut down power to the street Feb. 20 / 21 to install a generator that will provide power to the site for approximately one week.
Alex Corbett provided an "Open Space" tour of the project which can be viewed towards the end of the meeting recording.
January 12, 2023
Brian Hromadka of CBRE/Heery reported that good progress is being made. The project is on budget and on time. Work has been performed on some Saturdays to make up for delays and will continue where beneficial. Brian, along with the City, have been working with the MSBA on invoice submission through their payment system to facilitate MSBA reimbursement for applicable costs.
Supt. Lummis reported that the new school building was toured by East Gloucester and Veterans' Memorial Schools staff who were excited to see the building coming into form.
Michele Rogers from Dore & Whittier led a discussion and the Committee voted to approve numbering on some of the outside of windows as a safety measure.
Alex Corbett of WT Rich provided a construction update with an "Open Space" view of the interior of the building (the video can be viewed at approximately minute 50 of the meeting recording.) Tile has been started in the classroom halls, casework is being installed in classrooms, finishes are being applied in Building A bathrooms, insulation and wall board is being installed in the gym, and the administration area walls are taking shape.
December 8, 2022
The project remains on budget and on track for substantial completion in early June and as reported by Brian Hromadka of CBRE/Heery. While there have been delays due to staffing levels and materials, the project team is making up time with work on Saturdays when possible.
The School Building Committee discussed and approved adding cell service boosters in the building which costs approximately $100,000-$130,000 for implementation now vs costs that could be as high as $160,000 if this is added after construction is complete. Energy efficiency aspects of construction pose barriers to dependable cell service. The additional cost will be covered by the contingency budget.
CBRE/Heery has been submitting project invoices to the MSBA now that the Project Funding Agreement is in place. Reimbursement should start flowing in January for reimbursable costs to date.
Josh Perrine from Dore & Whittier presented the Furniture, Fixture and Equipment (FF&E) selection process and timeline. Costs are higher than in the past due to price increases and the incremental costs will be covered by the contingency budget.
Alex Corbett of WT Rich presented a drone video of the project which can be viewed here. He reported that the façade of "B Building" is getting finished off and they are working on getting the building totally enclosed for the colder weather. Finish work is underway in A Building.
November 10, 2022
Supt. Lummis reported that the Project Funding Agreement (PFA) has been signed by the Mayor and the Massachusetts School Building Authority. The PFA had been held up due to litigation that was recently fully resolved in the City's favor. With the execution of the PFA, the City will begin receive reimbursement from the MSBA for eligible project costs incurred to date and going forward. Owners Project Manager, CBRA/Heery has been working to get all past invoices submitted.
Brian Hromadka of CBRE/Heery reported that the project remains on track, but that there was some slippage in schedule due to labor shortages this past month that WT Rich will make up with additional manpower. The focus has been on getting the building closed up before the colder weather. Metal panels are being installed on the exterior and windows were scheduled to arrive next week. The project is now over 50% complete.
Tom Hood of WT Rich presented the Open Space view of the project which provides a detailed view of the interior of the building. He noted the gym is starting to take shape.
October 13, 2022
The project remains on schedule and on budget as reported by Brian Hromadka of CBRE/Heery. The project team continues to monitor material delays, but WT Rich, the construction manager, has been able to make accommodations to keep the project on track. Change orders are being managed closely. Almost $70,000 of scope has been able to be added back into the project. Please see Weekly Updates for more detail on work being performed.
Dore & Whittier has begun the furniture, fixture and equipment procurement process and has been working with the District on selections. Sample furniture options have been delivered to EGS and Veterans Memorial for educators to try out and provide feedback.
A drone video provided a nice view of the overall progress on the project.
September 8, 2022
Brian Hromadka of CBRE/Heery provided an overview of the project and reported that it remains on schedule and on budget. Delays in materials have been well managed by the project team to keep the project on track. The construction is approximately 50% complete.
Contracts awarded to Minority and Women owned businesses (MBE/WBE) is 16.4% of the total vs a target of 11.2%.
Alex Corbett of WT Rich presented an "Open Space" tour of the exterior and interior tour of the building, showing details of the brick and other finishes on the exterior and pointing out various aspects of the interior design taking shape. Temporary window coverings are being installed so that work on interior finishes can be underway.
9/8/22 Building Committee Packet
August 11, 2022
Brian Hromadka of CBRE/Heery reported that the project is tracking well and within budget. All subcontractor work has been awarded. The Committee reviewed four change orders, three of which were accounted for during the Value Engineering phase. The change orders included cost increases related to site conditions, changes in dry wall density in certain places, metal / soffit design and wiring. All change orders are within the project budget contingencies.
It was also reported that the Appeals Court affirmed the decision of the Superior Court in the Amaral v. City of Gloucester in which the City of Gloucester prevailed.
Project Photos & Videos
Flyby Tour of the proposed new East Gloucester/Veterans' Building
Interactive visioning workshop with project architects and designers. Building Committee members and the public were invited to view a series of "vision boards" and give feedback on a variety of images. This sparked conversation to begin defining design directions for the new school building, to ensure that the final design reflects the values, history, and unique qualities of the community, in addition to meeting our students' educational needs.
Overview of the new school's site layout for parking and drop off.
Need to translate this site?
For full functionality, configure your browser in the preferred language.Haga clic aquí para ver el sitio en español
Para una funcionalidad completa, configure su navegador en el idioma preferido.Clique aqui para ver o site em português
Para funcionalidade completa, configure seu navegador no idioma preferido.Clicca qui per vedere il sito in italiano
Per la piena funzionalità, configura il tuo browser nella lingua preferita.Nhấn vào đây để xem trang web bằng tiếng Việt
Per la piena funzionalità, configura il tuo browser nella lingua preferita.انقر هنا لعرض الموقع باللغة العربية
للحصول على الوظائف الكاملة ، قم بتكوين متصفحك باللغة المفضلة.